Bits on Bots

The scarcest thing in AI is now a permit

5 Nov 2026 · News

Chips, memory and power were each the bottleneck at some point. After Tuesday's elections, the hardest thing to get for a new AI data center is a government's yes.

The scarcest input in the US AI buildout is now permission. Texas has already stopped approving new data centers, and the governor-elect who beat Greg Abbott wants to keep that stop in place until the legislature writes new rules. Georgia and Ohio elected governors who promised pauses of their own. Voters turned down data centers in all but one of 41 local ballot measures. The building will go on. The advantage now goes to whoever already holds a site with power and permits, and the companies that need new sites wait.

Texas was already paused

The pause predates the election. In August Abbott ordered Texas grid regulators to audit every data center in line for a grid connection and stop advancing them in the meantime. On 21 September he went further and told the state environmental agency to issue "no permits sought by data center projects" until the audit is done, adding that "no state agency shall move forward with regulatory approvals." The line to connect had grown to about 474 gigawatts, roughly five times the state's record demand, and data centers made up about 90% of it. The audit is expected to finish in December.

That timing would have let the freeze lift after the vote. Gina Hinojosa, who takes office on 19 January, has said she wants the opposite. "When I am governor I will issue a moratorium, a ban, on all data center approvals until laws can be passed by the Legislature to protect Texans." Her campaign page calls a temporary pause that ends after the election "a scam." Republicans still hold the state Senate, according to Cleanview, which tracks data center projects. Lifting her pause would take a deal with them.

Georgia, Ohio and the ballot box

Fortune reports that Georgia's Keisha Lance Bottoms promised "a temporary statewide pause on new data center construction." Democrats also won a 3 to 2 majority on Georgia's utility commission, which sets the terms Georgia Power offers data centers. In Ohio, Amy Acton's platform backs "a conditional moratorium" until projects pay all of their utility costs, use union labor and build on old industrial land. She hasn't said whether she'd act by executive order, and Republicans kept both chambers there.

Local voters went further. CNBC counted 41 data center measures in 10 states, using Ballotpedia's list. Voters sided against data centers in every one except Harwood, North Dakota. Ohio had 21 of them. Cleanview notes that the megawatts directly blocked at the ballot box are small, at least 1.6 to 1.9 gigawatts. The bigger effect is on every county board deciding the next site. Cleanview also reports that on election night, Georgia's Effingham County tabled the site plan for OpenAI's 3.2 gigawatt Project Camellia until 17 November.

Who has a site, and who needs one

Cleanview counts nine states whose governor or governor-elect has promised or imposed a pause. Together they hold 158.6 gigawatts of planned data centers, 41% of the US pipeline. Bloomberg's estimate is wider. It puts about half of proposed US AI data center additions under tougher scrutiny, counting Texas, Georgia, Ohio and Pennsylvania. The two numbers differ on method, and both are estimates of exposure, not cancellations.

The 56.7 gigawatts already under construction nationwide are less exposed, because the pledges target new construction. Bloomberg quotes GLJ Research saying that in Texas, "projects with power, permits and steel keep going," while projects with power but no state environmental permit slip 12 to 18 months. A site that is already approved just became a scarcer thing to own.

Ben Thompson laid out who wins the morning after. Neoclouds, the companies that build data centers and rent out the chips, need new sites and new permits more than anyone, and have "much less political sway" than Amazon, Google or Microsoft, which "already have more sites they can repurpose or rebuild." He also expects AI "is going to have meaningful marginal costs for a long time to come."

Then and now

On 22 October we wrote that the model is the cheap part and that "whoever owns the slow part sets the pace." Back then the slow part was a wet lab, along with $5 billion of racks waiting on power. Now it's a state permit office.

On 3 November we wrote that the AI price war moved to the bond market, with neoclouds like CoreWeave and Nebius effectively shut out of new bond sales. Those same companies now face a second gate. On 4 November we wrote that the flat AI plan wasn't built for agents and that labs are starting to meter agent work. If new capacity arrives slower than planned, that meter is not going away.

Our call

On 30 June 2027, Texas will still have a statewide pause on new data center approvals in force, and so will at least one of Georgia or Ohio. A conditional moratorium counts if it blocks new projects until they meet new terms. We're wrong if Texas has lifted its pause by then, or if neither Georgia nor Ohio has put one in place. Construction already underway will keep going either way. Analysts at BMI told DCD that 2027 build schedules are "largely locked in," so the gap will show up in 2028 capacity that arrives late or somewhere else.

#infrastructure #news